Assignment Create Project, WBS, and CalendarIn Primavera P6, create a new Project as defined below.Project ID : ASGN7-Project Name : ASGN7 Project-Start Date : 1-Jul-25Project Must Finish by : BlankResponsible Manager : Accept the default choices for any other input.Create three (3) project-specific Calendars in Primavera P6 covering a period from Jan-2025 to Dec2028.1. 7 Day workweek calendar with no holidays or non-work periods. Name this calendar as’StudentName-7 Day Workweek No Holidays’.2. 5 Day workweek calendar with standard holidays and union holidays. Name this calendar as’StudentName-5 Day Workweek with Holidays’.3. Weather day calendar for the Los Angeles Civic Center, using random non-workdays per month basedon the WRCC historical record of 0.1inch or higher precipitation. Name this calendar as ‘StudentNameWeather Calendar’Create a WBS in the project using the following outline.